Project Details
Work Type: Widening
Phase: Completed
Length: 3.750 miles
City:
County:
Road:
Construction Cost: $20.43 Million
Project Start: Summer 2015
Est. Completion: Late 2018
About
This project consists of widening State Road (S.R.) 35 (Baseline Road) from Southeast 96th Place Road to south of S.R. 464 (Southeast Maricamp Road) from a two-lane to a four-lane roadway. Additional work includes sidewalks, drainage improvements, signing and pavement markings, guardrails, new signals and driveways.
Contact Information
Contractor
D.A.B. Constructors